Monitoring Well

Projects: Investigate and Monitor Well

Subsurface Investigations and Site Remediation

s

Situation

Dissolved phase industrial solvents were discovered by our client during periodic groundwater sampling activities at an existing network of groundwater monitor wells in the vicinity of an industrial park complex. ATC was contracted to conduct an area wide remedial investigation (RI).

Z

Results

ATC recommended a cost-effective, phased approach to complete the RI. The initial phase of the project involved historical research to identify previous and current tenants of the industrial park, installation of groundwater monitor wells, and development of an inexpensive sampling plan. ATC has installed 15 groundwater monitor wells as part of this RI in order to provide assurance that remedial activities are effectively removing contaminant mass. Groundwater monitoring and depth-specific sampling are still being conducted by ATC on a periodic basis.